Back to AMAFCA Current Projects

AMAFCA FY 2008 Project Schedule Page: 13

AMAFCA Project Manager: Christy Burton , P.E. or Jerry Lovato, P.E.

Design Engineer: Larkin Group NM

Construction Engineer: --

Contractor: --

Region: Northeast Albuquerque

District: 4 – Director Ronald D. Brown

Description: This project will construct a low-flow channel diversion and subsurface debris removal facility for storm water quality enhancement where the La Cueva Channel meets the North Diversion Channel.  The facility will provide storm water quality improvement and debris control to meet EPA permit requirements.

Current Status Report: In design, with some components being modeled by UNM.

Construction Schedule: To be constructed winter 2007-2008.

Public Meetings: None scheduled

Past Public Meetings: None

Available Documents: None

Figures:

Photos: